The opportunity to maintain the Riviera Bermuda from 3/8" to 2.0" is one of the key factors affecting playability.  With the current Fescue Rough, we are limited with mowing heights.  2.5" is about as low as we can go.  With the Riviera withstanding heights as low as 3/8", we will now be able to cut walking paths from tee to fairway, as well as Chipping Areas around greens for more variety of shots.  The buried lie six feet off the green is hopefully a thing of the past!

We also reviewed the schedule for the project.  Below is the approximate outline.
  • May 15:      Begin painting borders of the area to be killed.
  • May 20:     First application of Roundup
  • June 9:       Second application of Roundup.
  • June 23:    Third application of Roundup, if necessary.
  • June 30:    Begin seedbed preparation.  Scalping, verticutting, leveling, etc.
  • July 7:        Seed Rough.  Golf Course Closed for Four Weeks.
  • Aug. 5:       Golf Course Open.
The four week schedule is a tight window from seeding to opening.  I expect the course to be playable, but expectations should be lower during the first couple of weeks after opening.  With carts limited to the path and the normal reduced rounds we see in August, I don't foresee any setbacks due to opening.  Worst case scenario is we move tees to the start of the fairway for a short period of time while we continue to push the grow-in.

One of the topics we discussed last night was the Native Areas.  As part of the project we will be killing off areas of Native that have been taken over with Bermuda.  These areas will either be seeded during the project or later in the fall, depending on the area.  One of the primary concerns is adjusting the locations to eliminate balls reaching the Native more often than we would like to see.  The top of the list for changes are right of #10 green, left of #4 fairway, and right of #7 fairway.

Please pass along ideas or concerns you have regarding the Native.  This has been a frequent topic of discussion that I want to make sure is addressed properly during the project.

Thank you for your interest in the project and please do not hesitate to contact me if you have any questions or concerns.